Every summer for the past several years, more than 4,000 cyclists a day have pedaled up McGuinness Boulevard between the Pulaski Bridge and Meeker Avenue, sharing the road with box trucks, film equipment vans, and drivers cutting through Greenpoint to avoid the BQE. The corridor's redesign changed over several years, and in January 2026 Mayor Zohran Mamdani announced the city would complete the original plan.
The history of those changes begins with the safety plan developed in response to concerns about the corridor.
The Danger Was Never In Dispute
Nobody who has lived near McGuinness Boulevard needed a study to tell them the road was hazardous. In May 2021, a teacher was struck and killed crossing the street by the driver of a Rolls Royce.
The city's own numbers back up the fear. McGuinness carries more than 4,000 daily cyclists during summer months, making it one of the busiest bike connections between Brooklyn and Queens, and DOT officials have described it for years as dangerous for bikers, pedestrians, and drivers alike. By 2023, the pressure from parents, advocates, and Assemblymember Emily Gallagher had produced a real plan: strip a lane of traffic in each direction and build protected bike lanes the full length of the corridor, from Meeker Avenue to the Pulaski Bridge.
That plan lasted less than a year.
The Project Plan and Its Changes
The Adams administration replaced the 2023 plan with a scaled-back version that split McGuinness into two differently designed halves, adding a bike lane to part of the corridor without removing any travel lanes. At the time, officials cited community feedback. The project later became part of a criminal case.
Tony and Gina Argento, who run Broadway Stages, opposed the original redesign, arguing that the road diet would slow trucks hauling equipment to sets around the city. Separately, an indictment unsealed in August 2025 accused Ingrid Lewis-Martin, a top aide to then-Mayor Eric Adams, of taking bribes in exchange for the Department of Transportation withdrawing support for the project.
What the Project Will Deliver This Fall
Mamdani made McGuinness Boulevard the first project he revived after taking office, holding a press conference at Father Studzinski Square on January 3, 2026, days into his term, to announce the city would deliver the original plan in full. Construction broke ground on May 27, 2026, with DOT Commissioner Mike Flynn and Deputy Mayor Julia Kerson joining advocates at the site. Kerson, who grew up nearby, told the crowd she remembered pulling U-turns as a kid rather than crossing McGuinness on foot, and recalled a Blockbuster down the road she was never allowed to walk to because the street was considered too dangerous.
Once finished, the corridor will carry one travel lane, one parking-protected bike lane, and one parking and loading lane in each direction, the full length from Meeker Avenue to the Pulaski Bridge. That extends the parking-protected lanes already running between Meeker and Calyer Street north to the bridge, closing the gap that the scaled-back 2024 version left open. The city has also promised shorter pedestrian crossing distances and traffic-calming measures at turns, changes DOT has cited as capable of cutting severe injuries and fatalities by up to 30 percent based on similar redesigns elsewhere in the city.
On timing, the city's own announcements have not been perfectly consistent. Flynn said in late May the work should wrap in about three months, which would put completion near the end of August. Other city communications and coverage since then have framed the target as early fall. Either way, residents walking or biking the corridor this month should be seeing the finished configuration, or very close to it, for the first time since the project was first promised back in 2023.
Not everyone is convinced the fix solves the underlying problem. Barney Dombrowski, a 76-year-old pedestrian who spoke to reporters at the groundbreaking, said he was optimistic the plan would reduce the number of vehicles during peak hours, calling it a definite improvement. That's a modest claim from someone who has watched this project get promised and scrapped more than once.
A Mural Marks the Project
The most visible sign that the project actually happened isn't a bike lane. It's a mural.
At Father Studzinski Square, the same spot where Mamdani held his January press conference, DOT commissioned artist Kevin Cincotta to design a temporary installation covering 1,600 square feet of asphalt and 80 linear feet of concrete bike barrier. The design draws on Greenpoint's history as marshland before it was filled and developed, along with the neighborhood's Polish heritage. City Council Member Lincoln Restler called it a tribute to that history painted onto what had been bare asphalt and concrete.
It's a small addition to the completed redesign, but it marks the corridor as something other than a through-street for the first time. State Senator Kristen Gonzalez, whose district includes the area, described the goal as turning a long-divided roadway into a place residents can recognize as their own, not just a route they use to get somewhere else.
Why Other Neighborhoods Are Watching
Advocates who fought for the McGuinness redesign are already talking about it as a template rather than an isolated fix. Bronwyn Breitner, coordinator of the Make McGuinness Safe coalition, said she hopes DOT uses the completed project as a model for other corridors, calling it a precedent for similar streets citywide. The Mamdani administration has pointed to a parallel case in the Bronx, where redesigned bus lanes along Fordham Road faced years of opposition from the New York Botanical Garden, Fordham University, and the St. Barnabas Hospital Health System before moving forward under the new administration.
For Greenpoint, the practical result is a street that finally matches years of promises. The project also offers other neighborhoods an example of a street-safety redesign that moved from proposal to construction.
If you're weighing a move to Greenpoint or already call the neighborhood home and want a clearer read on how projects like this shape property values and buyer interest along the corridor, Asset CRG tracks these changes as part of its work across North Brooklyn. Reach out to request a property valuation and off-market access to opportunities near the corridor before the next phase of change lands.